Applied Digital said October 2 that the second phase of Building 2 at Polaris Forge 1 in Ellendale, North Dakota, reached Ready for Service, adding 75 MW of critical IT load across three 25 MW data halls.
Capacity delivered versus planned buildout
The company says the milestone brings its operational campus total to 250 MW and that the fully leased campus is contracted to deliver 400 MW at full buildout. These figures come from Applied Digital’s investor release and are not independently audited in this review.
The image is an earlier company photograph from the Ellendale campus, not the halls brought online in October. It provides site context only; it does not depict the newly delivered 75 MW phase.